Provisional Sums in Construction

Provisional Sums are budget allowances for uncertain work in construction. Once instructed, they become variations that can impact cost and schedule.

Team ConInnova

Jan 28, 2025

Share via:

In construction contracts, Provisional Sums (PS) play a critical role in managing scope uncertainty and budgeting for future instructions. But how well do we understand their types and impact?

What are Provisional Sums?
These are allowances included in the Schedule of Quantities (SOQ) or pricing documents for works that are undefined or uncertain at the time of contract signing. They’re only executed once the Engineer or Employer gives the green light.

Types of Provisional Sums:

  • Defined PS: Scope is known but price or final details are pending.

  • Undefined PS: Scope is unclear; valued based on actual cost + overheads.

  • Prime Cost Sums: Specialist subcontracted work (e.g., lifts, MEP); adjusted as per supplier cost + contractor’s margin.

  • Contingency Sums: For unforeseen or minor adjustments not covered in the original scope.

When Does It Count?
A PS item becomes payable only when instructed. Until then, it’s just a placeholder. Once activated, it’s treated as a variation and priced accordingly.

Project Impact:

  • It becomes a variation and is evaluated using actual costs + agreed markups.

  • Contractors must provide detailed breakdowns to support Employer decision-making.

Treat Provisional Sums with care, they may look passive on paper but can have active consequences on cost and program”.

Brand logo

Subscribe to our free bi-monthly newsletter for updates on construction innovation and cost management across New Zealand.

Subscribe to our free bi-monthly newsletter for updates on construction innovation and cost management across New Zealand.

We care about your data in our privacy policy.

ConInnova HQ

Level 5, 3 te Kehu Way,

Mount Wellington, New Zealand

ConInnova Sri Lanka

No. 328/3 Temple Road, Kaduwela Rd,

Battaramulla, Sri Lanka

ConInnova UAE

Meydan Grandstand, 6th floor, Meydan Road,

Nad Al Sheba, Dubai, U.A.E.

ConInnova, all rights reserved, 2025

Connect with us:

Brand logo

Subscribe to our free bi-monthly newsletter for updates on construction innovation and cost management across New Zealand.

Subscribe to our free bi-monthly newsletter for updates on construction innovation and cost management across New Zealand.

We care about your data in our privacy policy.

ConInnova HQ

Level 5, 3 te Kehu Way,

Mount Wellington, New Zealand

ConInnova Sri Lanka

No. 328/3 Temple Road, Kaduwela Rd,

Battaramulla, Sri Lanka

ConInnova UAE

Meydan Grandstand, 6th floor, Meydan Road,

Nad Al Sheba, Dubai, U.A.E.

ConInnova, all rights reserved, 2025

Connect with us:

Brand logo

Subscribe to our free bi-monthly newsletter for updates on construction innovation and cost management across New Zealand.

Subscribe to our free bi-monthly newsletter for updates on construction innovation and cost management across New Zealand.

We care about your data in our privacy policy.

ConInnova HQ

Level 5, 3 te Kehu Way,

Mount Wellington, New Zealand

ConInnova Sri Lanka

No. 328/3 Temple Road, Kaduwela Rd,

Battaramulla, Sri Lanka

ConInnova UAE

Meydan Grandstand, 6th floor, Meydan Road,

Nad Al Sheba, Dubai, U.A.E.

ConInnova, all rights reserved, 2025

Connect with us: